Jacobs and TYLin get up to $150M to help Washington's airports manage overlapping builds

The Metropolitan Washington Airports Authority hired Jacobs and TYLin under task-order contracts capped at $150 million over five years, expandable to $300 million over 10. The authority is paying for extra staff to handle overlapping work. Dulles' Package T tunnels must fit with three other construction packages, while Reagan National's Terminal 1 procurement runs in parallel.

This story was produced through MarketScale. See how Engineering & Construction teams put it to work with Partner & Channel Enablement.

By MarketScale Newsroom · JacobsTylinMetropolitan Washington Airports AuthorityDulles Package T
Share
Jacobs and TYLin get up to $150M to help Washington's airports manage overlapping builds

Key takeaways

01

Washington's airport authority secured up to $150 million of outside program management before Dulles' Package T tunnel work has been solicited, because it expects simultaneous projects to exceed its own staff and existing contractors.

02

Even at its full 10-year, $300 million ceiling, the oversight pool serves a Dulles redevelopment valued at more than $20 billion, and it also covers Reagan National.

03

The first task orders will show whether Jacobs mainly leads Package T or provides staff across both airports. Package T responses are due Nov. 23 and Reagan National construction manager at-risk proposals are due Dec. 7.

Free workspace

Turn your Engineering & Construction expertise into content.

Record interviews, organize footage, and write with AI on a free trial of the MarketScale platform for qualifying companies. No demo required, no credit card.

Try it Free

The authority that runs Washington Dulles International Airport says extended train tunnels and a new underground network will eliminate the need for mobile lounges and plane mates to carry passengers. The network would link concourses that sit as far as about 3,500 feet apart. On Nov. 17, Jacobs said it will help manage that work.

The contract runs five years and covers both Dulles and Ronald Reagan Washington National. Dallas-based Jacobs Project Management Co. and San Francisco-based TYLin International each received their own task-order contract from the Metropolitan Washington Airports Authority (MWAA), Engineering News-Record's Bryan Gottlieb reported, citing procurement records. Under a July 15 board resolution, combined spending is capped at $150 million over five years. If MWAA exercises five one-year options, the ceiling could reach $300 million across a decade.

The structure tells the story. MWAA locked in up to $150 million of outside program managers while Package T was still at the request-for-information stage, because the authority expects its simultaneous projects to outrun its own staff and existing contractors. That matters to contractors chasing the Dulles tunnels or the Reagan National terminal. For years, the people administering their contracts could come from these two firms.

How the $150 million ceiling gets spent

Neither firm is guaranteed $150 million, or any fixed share of it. MWAA pays only as it issues task orders, and specific assignments haven't been disclosed. The July board action, Resolution 26-9, sets the figure as an estimated not-to-exceed spend, and its title describes the award as program management support and staff augmentation services. That second phrase suggests much of the money buys people who work inside MWAA's own organization rather than standalone deliverables.

The scope is broad. It covers construction management, contract administration, project controls, finance, environmental reviews, engineering oversight and planning. Jacobs' own announcement also lists staff augmentation for administrative and technical engineering tasks.

The program those people will serve has grown fast. ENR puts the Dulles redevelopment at more than $20 billion, up from about $7 billion before the U.S. Department of Transportation selected a proposal in July. Construction Dive's Sebastian Obando put the overhaul President Donald Trump unveiled that month at $22.5 billion. That plan followed a DOT review of more than 30 proposals submitted the previous December. The two outlets' totals differ, but both describe a program roughly triple its earlier size.

The oversight pool against the work it supports

$150M
Combined spending cap for Jacobs and TYLin over the first five years, paid per task order
$300M
Maximum ceiling if MWAA exercises all five one-year options over 10 years
More than $20B
Value of the Dulles redevelopment the contracts help oversee
$4.5B to $5B
Dulles Package A, covering 2.5 million to 3 million sq ft of terminal and passenger-processing space

Metropolitan Washington Airports Authority; Engineering News-Record

Spread evenly, the initial ceiling comes to about $30 million a year across both firms. That figure is simple arithmetic on MWAA's cap, not a spending rate the authority has published. Actual spending could cluster around whichever packages are in design or under construction at a given time.

Even at the full 10-year ceiling, the pool tops out at $300 million. The Dulles program alone is valued at more than $20 billion, and the contracts also cover Reagan National. Airport capital directors elsewhere shouldn't read the pool as a full program-management budget. MWAA is adding these contracts to its own employees and existing contractors, so the figure suggests only what it is spending on extra staff.

What the Dulles money builds

Jacobs' release sketches the scope at Dulles: new international and domestic concourses, an expanded central processing area, updated check-in, security and baggage systems, and new concourse connectors meant to give travelers more predictable routes. Inside the concourses, it promises expanded gate areas, with new retail and dining placed in high-traffic zones. ENR reported in July that Package A would add or renovate gates, security areas, baggage systems and a post-security connector to Concourse A.

All of it wraps around a building that stays. ENR notes that the Eero Saarinen-designed main terminal will be preserved, and Jacobs Chair and CEO Bob Pragada described the work as "blending thoughtful modernization with the timeless architecture that makes these spaces unique." For oversight staff, that means new capacity added around and beneath a landmark that keeps operating while the work goes on.

Package T and its underground neighbors

In Jacobs' announcement, MWAA President and CEO Jack Potter singled out Package T, the extension of Dulles' underground train and related work. He called it a key part of the authority's Dulles Global Gateway initiative and cited Jacobs' experience on MWAA's Metrorail Silver Line construction, saying the firm "will be instrumental in moving this important project forward." MWAA issued a request for information on Oct. 21. It asks prospective progressive design-build teams for input on scope, procurement strategy and construction risk.

ENR's account of the request breaks the package into an extension of the existing system and a new network:

  • Extending the automated people mover to Concourse C West and Concourse D West with new tunnels and systems, work that procurement documents call Tier 2 and Tier 3
  • Tunnels linking Concourses A, C and D so passengers can move between them without going back through the main terminal
  • Links that take international arrivals out of Concourse C to a planned federal inspection facility
  • An underground baggage system connecting the main terminal with the concourses

Timing is the hardest part. According to MWAA, three other major construction packages will be underway while Package T is being designed and built. Tunnels, stations and concourse structures have to be coordinated so finished work doesn't have to be redone. Package A, the terminal procurement, leaves out the major AeroTrain extensions, but its infrastructure still has to be built to accept those future connections. Handoffs like these fill the days of project controls and contract administration staff.

Concourse A shows where the seams could fall. Package A carries the post-security connector to it, while Package T's tunnels would tie it to Concourses C and D, so two separately procured packages would converge on the same concourse.

The request reflects the same concern. It asks for recommendations on utility surveys, construction logistics, contract structures and risk allocation. It also asks firms to describe their experience with underground stations, tunnel ventilation, life-safety systems, baggage conveyance and construction inside an operating airport.

Steve Pelham, Jacobs' aviation market director for the Americas, said in the release that modernizing airports while they stay fully open requires careful sequencing and close work with the operator, the airlines and the delivery teams. He named United Airlines among the stakeholders. Jacobs also says the program leaves room to explore high-speed moving walkways and small autonomous shuttles.

Reading Jacobs' role

Potter's comments could point to a different role. He tied Jacobs directly to Package T, which suggests at least part of the firm's work could be leading a single package rather than lending staff across both airports. Construction Dive read the statement the same way, reporting that Jacobs will assist with Package T at Dulles. The resolution allows for either, and the early task orders will show which one MWAA chose.

Jacobs also arrives with history at the authority. Commercial Construction & Renovation reported that MWAA earlier selected Jacobs for facilities condition assessment and enterprise asset management services at both airports. That work covered how buildings and infrastructure are managed, capital investment needs and which maintenance and repair projects come first. It used the same architecture as the new award: a five-year term built from a base year plus one-year options.

Beyond Washington, Jacobs says ENR has ranked it No. 1 in aviation for the second consecutive year and that it works at more than 150 airports. Its U.S. list includes Hartsfield-Jackson Atlanta, Los Angeles International, Denver International and the terminal expansion at Baltimore/Washington International Thurgood Marshall.

Reagan National on a parallel track

At Reagan National, MWAA plans to replace the older Terminal 1 gate for gate and redevelop the airport's South Area. Airport manager Terry Liercke told ENR in a July 2025 interview that a design firm had been chosen for the replacement terminal, which will connect to the historic 1941 terminal building. He said the issues under review include security checkpoints, ticket counters, baggage claim and roadway access.

An Oct. 9 solicitation seeks a construction manager at-risk for preconstruction planning and construction support on Terminal 1 and the South Area. Proposals are due Dec. 7. Because the scope starts in preconstruction, the winning team would be involved early, working beside whatever oversight staff MWAA assigns through the Jacobs and TYLin contracts. Builders pursuing both airports will be dealing with the same owner, the same pool of outside oversight staff and procurements that overlap.

Teams answering the Package T request or the Reagan National CMAR solicitation can ask MWAA a direct question: which firm's staff will run project controls and contract administration on this package, and how task orders will split between the two airports.

Two deadlines before year end

Package T responses are due Nov. 23, four days from now. MWAA will use them to shape its procurement strategy, and the request isn't a construction solicitation or a contract award. Reagan National's CMAR proposals follow on Dec. 7.

After that, watch the first task orders issued under the July resolution. Whichever firm gets the work where Package T meets Package A will show how MWAA plans to manage four construction packages in the same ground under Dulles.

Featured companies

Your experts belong here

Every story in MarketScale Engineering & Construction starts with a company putting its project engineers, superintendents, and estimators on the record. Buyers are already reading this topic. The only question is whose experts they find.

Owners shortlist firms they already trust, and your field leaders become the reason your name is on that list.

Book DemoSee how it works15 minutes, straight to a calendar.

About the author

MarketScale Newsroom
MarketScale NewsroomEditorial Team, MarketScale

The MarketScale Newsroom reports on the companies, technologies, and trends shaping 16 B2B industries. It turns primary sources and expert commentary into clear, useful coverage for the people doing the work.

B2B Weekly

The week in Engineering & Construction, and sixteen other industries, every Monday.

Ten stories, one-line takes, five minutes. Free.

Engineering & Construction: are you visible to AI?

Before they reach out, Engineering & Construction buyers ask AI engines which vendors to trust. Explore how your experts, customers, and partners can become useful content for buyers and AI search.

Free Trial

You just read one Engineering & Construction expert. Your company is full of them.

This article was produced through MarketScale. The same platform turns your project engineers, superintendents, and estimators into the articles, video, and social content Engineering & Construction buyers are searching for. Start a free trial and see it with your own people. For qualifying companies, no credit card, no demo required.

NPS +73 · 1,000+ creators · 38+ countries

What your free trial includes

Hands-on access to the MarketScale platform
Media requests to your crowd, remote recording, AI writing tools
No demo required. No credit card.
For qualifying companies. Company confirmation required.

More Engineering & Construction Insights

Autodesk Forma's November update lets admins assign project access through Autodesk Assistant

Autodesk Forma's November update lets admins assign project access through Autodesk Assistant

Autodesk's November Forma release includes construction updates, many of them useful to administrators running large project portfolios. Administrators can add existing hub members to multiple projects through Autodesk Assistant and push template updates to hubs that already have them. Closeout gets handover exports filtered by location.

  • 01Authorized Forma administrators can add existing hub members to multiple projects through Autodesk Assistant on manage.autodesk.com. The feature is initially available to eligible customers with projects hosted on US servers.
  • 02Forma can automatically map Revit levels and areas into the Location Breakdown Structure, and handover exports can be filtered by Location—so teams that set up Locations early may be able to reuse that structure to organize closeout packages.
  • 03Assistant's new PDF reading takes one file at a time, up to 4.5 MB, and keeps it out of the project record. Any answer the project needs on file still has to be saved there by hand.

Nov 18, 2026

About half of mechanical contractors rate BIM-to-shop links highly

About half of mechanical contractors rate BIM-to-shop links highly

Nearly all mechanical contractors that use BIM already model, and 86% have linked BIM to fabrication software. Only about half say that link works well. MSUITE's workflow guide proposes dated work packages, with need dates taken from the field's install sequence and field issues sent back to VDC tied to each package. The reason: fabrication lead times run three to six weeks, install sequences change routinely, and the shop can be the last to hear.

  • 01Nearly every mechanical contractor already models; the weak point is the wire to the shop, which 86% have installed and only about half say works well.
  • 02The next gap sits one link further down: only 35% of contractors say their BIM and fabrication links to ERP and project management systems work well.

Nov 18, 2026

Why the Ellison Institute's 80-metric-ton sun-tracking dome is built to move slowly

Why the Ellison Institute's 80-metric-ton sun-tracking dome is built to move slowly

Crews in Oxford have removed the membrane from the Ellison Institute of Technology's 20-meter observatory dome, showing an 80-metric-ton steel frame that rotates to shade the glazed timber shell. The frame could turn fully in 10 minutes but is designed for tiny sun-tracking steps. Precision is the hard part.

  • 01The Ellison dome's 80-metric-ton steel frame could spin a full circle in 10 minutes, and it is engineered to spend its days creeping after the sun in small, exact steps.
  • 02For kinetic shading, the useful questions concern positioning accuracy, repeated start-and-stop cycling, behavior in occupied rooms, and long-term noise, reliability and maintenance—not just how fast the frame can rotate.
  • 03Comfort and energy gains from the rotating shade are design intent until the building runs through full seasons, so operating data is the signal that will confirm or complicate the case.

Nov 17, 2026

Explore More Engineering & Construction Insights

Read more expert perspectives from across Engineering & Construction.

Browse Engineering & Construction Hub

About the Expert

MarketScale Newsroom
MarketScale Newsroom

Editorial Team

MarketScale

The MarketScale Newsroom reports on the companies, technologies, and trends shaping 16 B2B industries. It turns primary sources and expert commentary into clear, useful coverage for the people doing the work.

For B2B teams

Your experts could be publishing here

Stories like this one run on content MarketScale captures from real practitioners. See how your team's expertise becomes coverage in Engineering & Construction and beyond.

Book a Demo

Or call us. No forms required. We pick up. 214-945-2512