How Kaufmann fits a timber module factory into six trucks
Kaufmann Bausysteme sets up timber module production in rented industrial halls near large projects, moving its equipment in six trucks within three weeks. The Austrian builder's rail-fed line delivers about one module an hour at up to 95% prefabrication. Kaufmann now wants to license that process abroad, charging per module.
This story was produced through MarketScale. See how Engineering & Construction teams put it to work with Partner & Channel Enablement.
Key takeaways
For large timber-module runs, Kaufmann avoids long-distance shipping of finished modules by moving its production setup instead: the equipment fits in six trucks, production can start in a rented hall within three weeks, and the setup can be dismantled within a week.
The portable part is the documented process. Prescribed workstation tasks, a QR code per module and photo records at each stage let a newly trained local crew turn out the same module in a rented hall.
A per-module licence fee is the milestone to watch: Kaufmann is exploring a franchise model, and if the Montana support or New Zealand enquiries become a signed licence, its manufacturing playbook and digital system could become something other builders license and pay for per module.
Free workspace
Turn your Engineering & Construction expertise into content.
Record interviews, organize footage, and write with AI on a free trial of the MarketScale platform for qualifying companies. No demo required, no credit card.
Six trucks. That's all it takes for Austrian modular builder Kaufmann Bausysteme to move the equipment that turns a rented industrial building into a timber module plant, and the company can set up production there within three weeks.
The idea came out of necessity. Kaufmann's first big school project in Berlin needed more than 400 timber modules, and shipping finished modules from its plant in Kalwang, Austria, didn't make economic sense. So the company set up production in Berlin. It did the same in Rostock, in northern Germany, after it won a customs school contract for about 1,000 modules.
Kaufmann found that shipping completed modules long distances didn't pay, so it moves the factory instead. Its manufacturing equipment travels in six trucks. Production can start in a rented industrial building within three weeks, and the setup can be dismantled within a week. For anyone who runs an offsite plant, or buys from one for a big public program, the useful question is what makes a factory light enough to move. Kaufmann's answer is mostly a production system.
What travels in the six trucks
Kaufmann doesn't build factories. It looks for existing industrial buildings near the project with enough floor space and overhead crane capacity, then hires local workers and subcontractors. Its own construction and project management teams train the new crew and support production in the early weeks. Cross-laminated timber components arrive at each site already prefabricated for assembly, while design and planning stay at headquarters in Reuthe, Austria.
It helps to separate this from the familiar idea of relocatable modular buildings. The International Code Council, as Built America Magazine notes, describes those as partially or completely assembled buildings designed to be reused and moved to different sites. Kaufmann flips the arrangement: the building stays put for good, and the factory is what moves.
The material flow follows the same logic. Built America points out that panelized components ship flat and travel more efficiently than volumetric boxes, which can need special permits and escort vehicles on the road. Kaufmann appears to get the benefit of both: prefabricated timber components make the long trip, and the bulky, nearly finished box only travels the short distance from the rented hall to the site.
On the floor, modules move on rails through a series of workstations, and each station carries out a set list of assembly and fit-out tasks. The line is reported to finish one module an hour, with prefabrication reaching up to 95%. Every module gets a QR code that links to its design and manufacturing data, and each production stage is photographed and logged in Kaufmann's in-house digital system.
That documentation does most of the work. A crew hired last month in a new city can build the same module as a veteran team in Kalwang only if each task is written down, sequenced and checked. Seen this way, the rented hall is mostly an assembly station running a playbook written in Reuthe.
Kaufmann builds three module types: closed, semi-open and open, covering everything from single rooms to larger shared spaces. Module sizes follow a flexible grid set by transport logistics, not a fixed module size, so the road still shapes the design when the plant sits close to the site.
The 95% figure is high by general industry standards, though the measures differ. Built America Magazine describes volumetric modules as typically arriving 50 to 90% complete. Mordor Intelligence, in its Central and Eastern Europe prefab market report, puts the share of productive work that factory production can shift into controlled settings at 60 to 90%. These are different measures, so treat the comparison as directional. It does suggest that Kaufmann doesn't give up completeness when it builds in a borrowed building.
High completeness has a side effect. Built America notes that because wiring and plumbing sit behind finished surfaces in volumetric modules, inspections often happen at the factory rather than on site. A photo record of every production stage could therefore matter beyond internal quality control, wherever an inspector needs to see work that is already closed up.
Matching capacity to the order book
Kaufmann Bausysteme's production network
Built Offsite
Set next to the capacity figure, the forecast suggests the network could be running well toward its stated maximum. Treat that as a rough read: the forecast dates from December 2025, the capacity figure from November 2026, and no utilization data has been published. In the same December 2025 update, Christian Kaufmann put the company's yearly cross-laminated timber needs at about 40,000 cubic meters.
The projects explain why each move made sense. Kaufmann had completed 35 Berlin schools over the previous six years. More recently it delivered the German federal president's temporary headquarters in Berlin, an 18,700 sq m, six-story building made of 382 timber modules produced at its Berlin-Herzfelde plant. Every relocation so far has been tied to a job in the hundreds or thousands of modules, or to a city with a steady stream of them.
That pattern suggests where the model fits. It looks strongest for public clients running multi-building programs, such as school or training-campus rollouts, where one site's setup cost is spread across years of repeat orders. For a single mid-size building, three weeks of setup and a newly trained crew would be harder to justify, and Kaufmann hasn't published where the cutoff sits.
Mordor makes a related point about public buyers in general: standardized buildings make repeat orders easier because manufacturers can reuse their engineering and production processes. Kaufmann's Berlin school run looks like that principle with one extra twist, since the production setup itself is reused from city to city along with the engineering.
Why fixed plants are hard to fund
The best numbers on fixed-plant economics come from a neighboring market. Mordor Intelligence's research covers Central and Eastern Europe, not the Austrian and German markets where Kaufmann's three plants operate. Read it as a picture of the pressures any fixed-plant builder faces in the region, not as a description of Kaufmann's own finances.
With that scope in mind, Mordor lists high upfront factory investment and scale thresholds among the restraints on the prefabricated buildings market in Central and Eastern Europe, and rates its impact on the CAGR forecast at about -1.3%. Mordor cites UIPI, which says standard construction financing doesn't meet the front-loaded cash needs of modular factories. Mordor also lists oversized-load logistics and site-access constraints, rated at about -0.6%, and names Poland-Germany, Romania-Hungary and intra-CEE transport corridors as relevant.
The report also gives a concrete case of the funding risk. ERBUD ceased investment in its modular business MOD21 in August 2026 after five years of cumulative losses, which Mordor reads as evidence of the risk of keeping factory capacity open without stable project demand. Mordor says the problem is most acute in Hungary, Slovakia and Romania, where demand pipelines can be less certain. That is the mirror image of Kaufmann's approach, which only stands up a line once a large order exists.
Built America Magazine describes the same transport problem from the US side: large volumetric modules can require special permits and escort vehicles. For operators who can find an existing industrial building near the site, Kaufmann's model could shorten the haul and avoid building a dedicated factory. Timber, Kaufmann's material, already held 37.8% of the Central and Eastern Europe prefab market in 2026, or USD 2.28 billion, according to Mordor, which also forecasts it as the fastest-growing material category at a 7.21% CAGR through 2032.
The model has real limits. It depends on finding a suitable building with crane capacity near the project, and on retraining a local workforce at every new site. A permanent plant with an experienced crew still makes more sense for scattered, smaller jobs where no single location has the volume to justify a move. The Kalwang plant still runs alongside the two German sites.
A licence fee on every module
The next step is to sell the playbook. Kaufmann is exploring a franchise model in which overseas construction businesses would license its manufacturing know-how and digital production system and pay a fee for each module produced. It has already supported a modular project in Montana, supplying its digital production tools and sending staff to help set up a local plant. New Zealand has also made enquiries.
International licensing represented only a small proportion of the company's revenue in December 2025, though Kaufmann identified it as an area for further business development. A per-module fee ties Kaufmann's income to the licensee's output instead of an upfront sale. That would matter to a builder who wants modular capacity without designing a production system from scratch.
Codes are where an exported playbook meets local reality. Mordor rates cross-border certification and national-code fragmentation at about -0.9% on its regional forecast and notes that producers exporting from Poland or the Czech Republic may still need country-specific engineering and certifications. In the US, Built America notes, modular homes are built to the same local and state codes as site-built ones. A production system can travel in a licence, but the module design it produces would still have to clear the rules where it is built.
Before signing for a relocatable or licensed module plant, ask three things: is there an available hall with enough floor space and overhead crane capacity within a short haul of the site, is the pipeline big enough to cover setup and training, and who carries the local code engineering for the module design?
The milestone to watch is a signed licence. If the Montana support or the New Zealand enquiries turn into a plant paying a fee on every module, Kaufmann's six-truck kit will have become a product other builders can buy.
Sources
Featured companies
Your experts belong here
Every story in MarketScale Engineering & Construction starts with a company putting its project engineers, superintendents, and estimators on the record. Buyers are already reading this topic. The only question is whose experts they find.
Owners shortlist firms they already trust, and your field leaders become the reason your name is on that list.
About the author
The MarketScale Newsroom reports on the companies, technologies, and trends shaping 16 B2B industries. It turns primary sources and expert commentary into clear, useful coverage for the people doing the work.