Only 1 in 15 Mexico hyperscale projects wins Fibra Mty sign-off
Fibra Mty reviews roughly 15 potential hyperscale data center projects in Mexico and typically signs off on one. Panelists said CFE/CENACE interconnections can take three to four years, so developers need a verifiable path to power—along with permits and water—before hyperscalers will sign build-to-suit deals.
This story was produced through MarketScale. See how Engineering & Construction teams put it to work with Partner & Channel Enablement.
Key takeaways
With grid connections in Mexico taking three to four years, the power path sets a data center's calendar before construction starts, and Fibra Mty passes only about 1 in 15 hyperscale projects it reviews.
Queretaro holds 72% of Mexico's active data center megawatts; Monterrey, Saltillo, Guanajuato and Jalisco work as alternatives only where transmission capacity and environmental permits check out site by site.
A sharper BTS-bid question: with roughly 42-week waits for transformers and switchgear, are long-lead power orders aligned to the same energization date as the grid connection?
Free workspace
Turn your Engineering & Construction expertise into content.
Record interviews, organize footage, and write with AI on a free trial of the MarketScale platform for qualifying companies. No demo required, no credit card.
Fibra Mty looks at 15 potential hyperscale data center projects in Mexico and typically signs off on one. André de Sousa, director of operations and business development at the Mexican real estate trust, gave that ratio on a panel at the Mexico Data Center Summit 2026 in Mexico City on November 25, as Mexico Business News reported. The other 14 fall out over energy feasibility, water scarcity, permitting delays and land title problems, often several at once.
He put the change in a single line: the business once revolved around square meters, and now it revolves around watts. That shifts what is really for sale for a developer holding industrial land in Queretaro, Nuevo Leon or the Bajio. According to panelists, hyperscale operators now expect a verifiable path to power, permits and water before signing a build-to-suit (BTS) agreement. Highway access and clean title will get a project into the first meeting. They won't get it signed.
A lot of money depends on that filter. The Mexican Association of Data Centers (MEXDC) projects more than US$18 billion in direct investment supporting as much as 1,516MW of new capacity in the country from 2025 to 2030. The Mexican Chamber of the Construction Industry puts the local data center construction market at US$1 billion in 2024 and estimates it could reach US$2.27 billion by 2030. The two figures measure different things, and neither organization reconciles them, but both point the same direction.
Grid timing sets the deal
Josué Ramírez, resource director for Latin America at DayOne, put the buyer's view plainly on the same panel: hyperscale operators don't buy land, they invest in places that can guarantee energy, connectivity and water. The sticking point is the grid. Connections through the National Energy Control Center (CENACE) and the Federal Electricity Commission (CFE) can take three to four years, so developers are weighing hybrid or behind-the-meter generation alongside grid redundancy to close the gap.
Juan Carlos Mondragón, MEXDC's president, described the same bottleneck in his opening address that morning. Interconnection for facilities above 100MW is the primary hurdle, he said, and high-voltage requests have at times held projects up long enough that developers paid for strategic energy infrastructure themselves. That matters because Mondragón also noted that AI gigacampuses start at 100MW and scale toward a gigawatt, which puts the next wave of demand squarely above the threshold where interconnection gets hard.
When a CFE grid connection takes three to four years and a transformer takes 42 weeks, the power path sets the calendar for a Mexican data center campus before anyone pours a slab.
Miguel Carreon, country manager and Latin America energy leader at AECOM, drew the planning consequence: industrial developers have to adapt their master plans to accommodate complex, high-capacity substations, and every project needs a demonstrable case that it can deliver at each stage on the promised timeline. De Sousa was more colorful, comparing piecemeal power fixes to cooling Azteca Stadium with mini-split air conditioners. For park developers, the practical reading is that the substation and the power study move from a utility line item into pre-marketing spend, paid before a tenant is in sight.
Where the megawatts sit today
Mexico had 279MW of data center capacity installed, 205MW under construction and 1,730MW announced through 2031, according to MEXDC figures from April 2026 that Mondragón presented. Built and under-construction capacity together come to roughly 484MW, so the announced pipeline is more than three times what exists or is being built today. Most of what exists sits in one state.
CBRE data cited during the panel shows Queretaro's market expanded 450.2% within one year. Grid congestion there is now pushing developers toward Monterrey, Saltillo, Guanajuato and Jalisco. Those corridors have established manufacturing clusters, but panelists stressed that transmission capacity and environmental authorizations have to be verified separately for every site. A strong industrial address does not pass its power position on to the parcel next door.
Large Queretaro projects show how power now arrives in tranches. CloudHQ's US$4.8 billion, six-building campus there is planned at 900MW with 200MW of initial power secured, Mexico Business News reported in October 2025, roughly a fifth of the eventual load. The campus was also announced with a waterless cooling design, a choice the outlet described as increasingly necessary in water-stressed regions.
The strongest objection to a corridor shift comes from Mondragón himself: client preferences ultimately decide where projects go. Queretaro's 72% share reflects where hyperscalers chose to build, and a secondary corridor with spare transmission still has to match the latency, fiber and ecosystem a client already has in place. Alternative sites widen the options. They don't replace the customer's own siting logic.
Ten months for a transformer
Even a site with a power path faces a second clock: the equipment. JLL's 2026 Global Data Center Outlook, cited in the panel coverage, puts numbers on the wait.
The equipment clock
JLL 2026 Global Data Center Outlook; MEXDC
Forty-two weeks is roughly ten months, which means long-lead orders for switchgear and transformers have to be placed well before a building permit is in hand if the energization date is going to hold. Mondragón added that copper shortages and demand for transformers and cabling have stretched procurement, and that domestic suppliers often cannot yet meet specifications for high-capacity power equipment, sending operators to Asia and other markets. Under Plan México and its Development Hubs for Well-Being, panelists noted, engineering, procurement and construction contractors face growing incentives to bring domestic suppliers into these supply chains.
The building itself has a shelf-life problem. De Sousa cautioned against taking on long-term financing for rigid facilities that could be obsolete within a decade as chip and liquid-cooling technology moves. Carreon made the matching design point: don't build around today's constraints for tomorrow's demand, and favor integrated project delivery with early commissioning. For lenders and owners, a shell that can take higher rack densities later is the asset that survives its own loan term.
Staffing becomes a site criterion
Ángel Pérez, associate director for data centers and industrial at Turner & Townsend, cited global survey data in which more than 80% of clients reported difficulty hiring qualified workers to build data centers. Specialized planners and systems integrators who can commission liquid-cooling systems and building management systems are the hardest to find. He also pointed to a less visible schedule risk: general contractors that reuse the same subcontractors on several projects without tracking how much capacity those crews actually have left.
The labor curve is steep at both ends. Mondragón said large construction phases have employed more than 4,000 workers on individual sites, while day-to-day operations for a 50MW facility need roughly 30 specialized staff. A small operating team carries a lot of weight: Ramírez said 70% to 80% of historical data center infrastructure failures trace to human error rather than equipment, which is why he argues for standardized operating procedures and putting operators in the room during commissioning.
Alejandro Luna, vice president for Latin America at UKG, framed workforce planning as a lifecycle job, from construction through 24/7 operations, with the aim of avoiding the double and triple shifts that create compliance exposure. MEXDC board member Luis Uribe said the association is building agreements with universities to develop the technical profiles the industry will need over the next 10 years.
Questions to settle before a BTS signature
The panel's points translate into a short pre-signing review for park developers and EPC contractors bidding hyperscale work. These are MarketScale's editorial suggestions built from the reporting, not a published requirement from any operator.
- Power path: is there a dated CENACE or CFE interconnection route, and if it runs three to four years, what hybrid or behind-the-meter supply bridges the gap?
- Long-lead gear: are transformers, generators, switchgear and chillers on order against the same energization date, given 42-week average lead times?
- Shell flexibility: can the design take liquid cooling and higher densities without a rebuild inside the financing term?
- People: do the general contractor's subcontractors have tracked capacity, and are future operators named for commissioning?
The first item does most of the sorting. A site that answers it with documents and dates belongs in the conversation Fibra Mty described; a site that answers it with acreage is still an industrial lot. Water and title checks still matter, but on the panel's account, power is where the 1-in-15 math is decided.
Ask the landowner which document proves the power path and what date it carries. If the honest answer is a three-to-four-year grid queue with no bridge supply, price the site as a future option, not a ready one.
The signal worth watching sits in Mondragón's own numbers. MEXDC now meets weekly with CFE, CENACE and the Ministry of Energy to line up grid expansion with private project pipelines. If a meaningful share of the 205MW under construction energizes on schedule and announced projects start converting outside Queretaro, those meetings are shortening the wait. If the 1,730MW announced figure keeps growing while installed capacity barely moves, power is still setting the pace.
Sources
Your experts belong here
Every story in MarketScale Engineering & Construction starts with a company putting its project engineers, superintendents, and estimators on the record. Buyers are already reading this topic. The only question is whose experts they find.
Owners shortlist firms they already trust, and your field leaders become the reason your name is on that list.
About the author
The MarketScale Newsroom reports on the companies, technologies, and trends shaping 16 B2B industries. It turns primary sources and expert commentary into clear, useful coverage for the people doing the work.