How KONE fits an elevator upgrade into one week of downtime
In an elevator modernization, field surveys, made-to-fit parts, security and fire alarm hookups, and code inspection still decide when riders get the car back.
This story was produced through MarketScale. See how Building Management teams put it to work with Customer Stories & Case Studies.
Key takeaways
A one-week elevator modernization covers the installation shutdown, while field surveys, made-to-fit parts orders and code inspection before and after it still set the real return-to-service date.
Single-elevator buildings gain the most from a short outage, and they still need an accessible alternative planned before crews arrive, because a sign pointing to the stairs doesn't count.
Free workspace
Turn your Building Management expertise into content.
Record interviews, organize footage, and write with AI on a free trial of the MarketScale platform for qualifying companies. No demo required, no credit card.
As little as one week of planned downtime. That's the promise on KONE's US modernization pages.
A KONE blog post, aimed at owners whose elevators are more than 15 to 20 years old, lists the familiar warning signs of an aging elevator: more service calls, parts that are harder to find, longer outages, passenger complaints and rising energy use. The argument is that a targeted upgrade of the parts that matter most can fix those problems without replacing the whole system, and without the weeks or months of disruption owners tend to expect. So two questions follow. What does the week actually buy? And what has to happen around it for the week to hold?
What gets swapped in seven days
The short install comes from a fixed core scope. According to KONE's one-week modernization page, every upgrade starts with electrification and signalization as the base. KONE says the package works on all major elevator brands, which matters to an owner whose building runs on another maker's equipment.
That structure explains how the timeline works. A fixed core lets crews repeat the same work from job to job, and owners pick the add-ons by priority and budget. KONE's own disclaimer is also clear that scope, timing, cost and results depend on equipment condition, the building and the code requirements in force. The word "eligible" in the pitch is doing real work, and an assessment decides whether a given car qualifies.
The same page lays the job out in three steps. Step one upgrades the key components, which KONE lists as electrification, controller, signalization, partial doors and power unit. Step two connects the elevator for real-time monitoring, so faults can be found and fixed before they become problems. Step three is the car back in service. The package menu on that page, meanwhile, treats a door system upgrade and a power unit upgrade as optional, so the line between base scope and add-on is worth pinning down in writing for each car.
The optional doors deserve a second look. Justin Gill, president of the New Jersey and Philadelphia service firm Allied Elevator, wrote in Construction Executive that door operators, controls, drives and power units can each have a different service life. He added that any proposal keeping existing equipment should say exactly what stays and whether the new parts can work with it. For an owner deciding whether to skip the door package, that advice suggests checking the condition of the door equipment first. Skipping it can be a fair choice, as long as the owner makes it with that information in hand.
The labor inside the week is specialized. The Bureau of Labor Statistics files major modernization and alteration, such as replacing electric motors, hydraulic pumps and control panels, under service crew work. Most states require elevator installers and repairers to be licensed, and nearly all learn the trade through an apprenticeship that typically runs four years. The whole occupation held about 24,700 jobs in 2025. A trade that size suggests the crew's start date belongs on the schedule as a confirmed commitment, not an assumption.
What KONE says the week buys
The pitch is also an argument about timing. KONE's one-week page says aging elevators are often patched for inspections, renewed too late and maintained only for the short term, and its blog adds that owners who wait for a major failure tend to meet their highest costs, downtime and tenant frustration at exactly that moment. On that reading, the planned week is being compared with an unplanned outage nobody got to schedule. The page then backs the case with three headline claims.
KONE's one-week modernization claims
KONE, one-week elevator modernization page
Read those tiles closely. On the page, the "up to 80%" and "up to 74%" labels sit under larger headline values of 58% and 52%, so each tile shows two different numbers for the same claim. An "up to" figure marks the best case in a range, and the predictive maintenance number depends on the step-two connection being in place, not on the hardware swap alone.
The calendar around the week
Gill's piece reads like a map of everything outside the installation window. Some modernization parts are chosen and built for the existing installation, so field measurements and decisions about how the new equipment connects often have to come before anyone can place an order. He advises tracking those steps separately from the shipping times a supplier quotes. Ordering early only helps if the design is settled. Equipment released before dimensions, electrical requirements and compatibility with retained parts are confirmed can lose the time it seemed to save once revisions start.
Getting the parts to the shaft is its own milestone. Gill notes that a completed lobby, a new storefront or an occupied loading dock can restrict how major elevator components move in and out, which turns finishes and temporary protection into schedule items. In a renovation where the lobby gets finished first, that could squeeze a one-week window from the outside.
His suggested milestone register runs from survey through design approval, submittals, release for fabrication, delivery, installation access, shutdown start, testing and final acceptance. A one-week install sits inside that list, roughly between shutdown start and testing. The seven days cover the shutdown, while the survey, the custom orders and the inspection before and after them decide the date tenants actually ride again.
The survey can also move the week itself. If it turns up an unanticipated condition, Gill advises recording the effect on equipment selection, budget, shutdown duration and other trade packages before anyone authorizes revised work. That's the moment an eligible one-week job shows whether it's still a one-week job.
The back end is where schedules usually slip. Gill points out that functional checks, integration with building systems, permit inspections, corrections and final paperwork all need coordinating. A missed inspection, or a fire alarm contractor who isn't available, can hold up the return to service after installation is finished. He suggests scheduling those steps as separate dependencies with named owners and inspectors, not one turnover date at the end of the Gantt chart.
Closeout belongs in the same register. Gill wants the owner handed updated equipment documentation, maintenance information, keys and operating instructions, and if maintenance responsibility moves between service firms, he wants that handoff deliberate and documented. That would matter in exactly the case KONE markets to: a package installed on another maker's equipment.
ASME A17.1/CSA B44, the safety code for elevators and escalators, covers alteration, testing and repair, so a modernization brings an inspection. Which edition applies depends on what the local authority has adopted. Confirm the approval process before promising tenants a return date.
Single-car buildings feel it first
A short outage helps most where there's no second elevator. Gill writes that a building with several elevators can't automatically take one out of service safely, because the remaining capacity and the floors each car serves still matter. In a building with one elevator, the owner may have to move some functions elsewhere or set up another workable way in. He advises bringing in property management and accessibility advisers before the contractor arrives, and he's blunt that a sign pointing to the stairs isn't an accessible alternative.
That's the human math behind the one-week pitch. It's far easier to plan, staff and explain a week of temporary arrangements for occupants with disabilities, deliveries and visitors than a month of them. A week still needs a plan, though, and Gill wants it in the contract documents: permitted work hours, site access, notices to occupants, emergency contacts, and who handles temporary barriers and signs. He also advises checking phasing assumptions against lease commitments and turnover dates, not leaving them to the contractor after the award.
Those lease commitments can be the reason the work is happening at all. Wellington Office Park in Amarillo, Texas, a 100,000-square-foot Class A building, lists elevator modernization among capital improvements underway, along with landscaping upgrades and renovated bathrooms. The listing also points to a brand-new roof, upgraded HVAC and a new security system. When an upgrade runs while space is on the market and tenants are in place, the length of the shutdown becomes a leasing question as well as a maintenance one.
The numbers on that listing make the point concrete. Four office spaces totaling 15,594 square feet are available immediately, all at $17.50 per square foot per year on full-service terms. A prospect touring one of them during a shutdown would meet the building through its temporary access plan. The listing also advertises a tenant parking garage with a locking security garage door, and a building with a secured garage, a new security system and an elevator modernization is where the next question would come up.
The controller swap meets the badge reader
Replacing an elevator controller also affects every system wired to it. Gill lists the trades a modernization may need: an electrical contractor, a fire alarm specialist, a security vendor and sometimes a structural trade, because controls can interact with emergency power and access systems. For each connection, he suggests asking who designs it, who supplies the equipment, who installs it, who tests it and who signs off. A general note telling one subcontractor to coordinate with others settles neither the cost nor the schedule.
The access side of that list is changing. Andrew Campagnola, director of product management at Kastle Systems, wrote in Security Sales and Integration that a typical downtown office tower might have one company's readers in the garage, another's at the lobby turnstiles and a third built into the elevators. Getting one person through all of them has traditionally meant the manufacturers sharing secret keys or paying middleware to load several credentials onto one phone. He argues the Aliro standard changes that: the private key stays on the phone, and the reader checks the credential using public information.
The Connectivity Standards Alliance, a group whose members include manufacturers, integrators and end users, released Aliro in February. Under the standard, a certified reader from any vendor will accept a phone or watch made by Apple, Google or Samsung, and the same credential can also be stored on a physical card. Campagnola's account of tenant expectations puts the elevator right in the middle: once tenants have signed a lease, they take it for granted that the badge for their suite will also get them into the garage and call the elevator.
Campagnola says certified readers and locks are reaching the market now, and he expects 2027 to be the year broad demand starts. He also notes that new readers generally read old cards and the new credential side by side, so a building can switch a floor or a tenant at a time. For buildings whose elevators carry access readers, that suggests the modernization interface is worth specifying with the next decade of credentials in mind. For buildings whose elevators have no access control, this part doesn't apply.
If the car carries access readers, ask the security vendor whether both the reader and the access control software behind it can handle credentials of 64 bits, 128 bits and beyond. Campagnola expects the 26-bit card number to go away fast, and a modern credential only helps if the system behind the reader can process it.
Questions to put to any bidder
Gill's checklist turns into a short set of questions for a one-week proposal, whoever's bidding. Which parts need field measurements before they can be ordered, and how long does manufacturing take after that? Which existing parts stay, and has anyone confirmed they'll work with the new controller? Who owns the fire alarm, emergency power and access control hookups, and who books the inspection? The answers show whether the single week sits inside a schedule that's already been settled.
Performance figures deserve the same care. The useful number for any owner is the one that applies to their own car, its age and its traffic, so it's worth asking for that figure in the proposal itself.
Sources
- Elevator Modernization in as little as One Week ↗
- Upgraded in one week | KONE modernization ↗
- Planning Elevator Modernization Without Derailing a Commercial ... ↗ · Construction Executive
- Access Control Was Closed on Purpose. It's Time to Open It. ↗ · Security Sales and Integration
- Wellington Office Park - 1616 Kentucky S, Amarillo, TX ↗ · Commercial Property Executive
Featured companies
Your experts belong here
Every story in MarketScale Building Management starts with a company putting its facilities engineers, energy managers, and service technicians on the record. Buyers are already reading this topic. The only question is whose experts they find.
Owners and facilities teams pick on trust, and your engineers turn that trust into inbound conversations.
About the author
The MarketScale Newsroom reports on the companies, technologies, and trends shaping 16 B2B industries. It turns primary sources and expert commentary into clear, useful coverage for the people doing the work.