Why electric yard tractors post 95 to 98% uptime in dedicated yards
Fleets running electric yard tractors posted 95 to 98% uptime in NACFE's report, and the tractors have done best in dedicated yards. That figure depends on predictable routes, charging windows and work. Site power often sets the schedule. Grid connections for fleet charging can take 36 months or longer, so Camber's Brendan Harney advises getting a power assessment from the utility before ordering tractors.
This story was produced through MarketScale. See how Transportation teams put it to work with Partner & Channel Enablement.
Key takeaways
Electric yard tractors post 95 to 98% uptime in dedicated yards, a reliability benchmark that holds where routes, charging windows and workloads are predictable.
Grid connections for fleet charging can take 36 months or longer, so the utility's capacity date, not the tractor delivery date, is the realistic start of a yard electrification project.
Software-capped charging, such as 1.4 MW of chargers limited to a 1 MW grid draw, offers a way to start a first group of electric vehicles on existing service while an upgrade is pending.
Free workspace
Turn your Transportation expertise into content.
Record interviews, organize footage, and write with AI on a free trial of the MarketScale platform for qualifying companies. No demo required, no credit card.
The argument now being made is that the strongest case for yard electrification today is operational. Sustainability still matters, but it is no longer the whole story.
For whoever runs a distribution center yard, the number settles an old question about whether a battery tractor can keep trailers moving to the doors. It also raises two sharper ones. Which yards produce that number? And how long does it take to get enough power to the site? The reporting suggests the second question sets the pace of a rollout more than anything on the tractor's spec sheet.
Where the uptime comes from
Buttgenbach is specific about the conditions behind the figure. Electric yard tractors have done best in dedicated yards where routes, charging opportunities and operating requirements are highly predictable. Yard performance is judged on service levels: trailers reach loading doors on time, and capacity is there when production schedules or shipping volumes change. That makes reliability the measure that decides adoption, and it explains why NACFE's range carries weight with operators who used to ask whether EVs could work in a yard at all.
That 95 to 98% belongs to the yard as much as to the tractor: predictable routes, predictable charging windows and predictable work. A tractor shuttling trailers inside one fence line never strays far from its charger, and its daily load is something a planner can model ahead of time. NACFE's range is a fair benchmark for sites that look like that. For a site with irregular schedules or awkward charger placement, it's a starting hypothesis rather than a promise.
Maintenance is the second half of the argument. Diesel yard equipment needs ongoing attention to engines, fluids, emissions aftertreatment and other wearing parts. An electric tractor drops oil systems, aftertreatment and engine-driven accessories altogether. Buttgenbach's point is that the lower repair bill matters less than the fewer service events. In a high-volume yard, a tractor in the shop means trailers waiting. So the saving is better counted as hours of availability returned to the yard schedule than as dollars off a parts invoice.
Then there are the people. Electric tractors run much quieter and produce no tailpipe emissions, which improves conditions for drivers, for technicians in the service bay and for warehouse staff working around docks and staging areas. Buttgenbach ties this to retention while labor remains hard to find. He also points to neighbors: yards near homes or dense population centers get less noise and fewer emissions at the fence line.
The utility sets the start date
Buttgenbach lists charging and utility availability among the factors that decide whether a site is ready, alongside duty cycles, schedules, layout and terrain. Brendan Harney, president of fleet charging operator Camber, explained in a March 2025 FleetOwner column why that factor tends to set the schedule. He said grid connection timelines can stretch to 36 months or longer, and that many utilities are only beginning to plan for fleet charging loads at the scale now arriving.
Harney cited recent ACEEE research showing that load from medium- and heavy-duty vehicles will be substantial, with new peak capacity needed for fleet charging by 2030. He also noted that the grid upgrades needed to meet that demand, from new substations to enhanced distribution feeders, can take five years or more to complete.
How much power fleet charging needs, and how long upgrades take
ACEEE research, as cited by FleetOwner
Harney's remedy is to reverse the usual procurement order. The traditional sequence of specifying vehicles, placing orders and preparing maintenance bays can leave a fleet with new vehicles and no way to charge them. His alternative starts with a power availability assessment at each facility, done with the utility, to establish grid capacity, required upgrades and a realistic delivery date. The vehicle schedule is then fitted to that date. For multi-site operators, he adds, utility readiness varies widely by region, so a network rollout could reasonably go in the order of utility readiness rather than in the order of operational priority.
His most transferable detail is a workaround. At a site for WeDriveU in San Jose, California, the utility needed more than a year to deliver the full power requested. Camber installed 1.4 MW of chargers anyway, with software capping grid draw at 1 MW, and got the customer's vehicles running while the upgrade went ahead. The same logic could apply in a yard, where a first group of tractors runs on the service the site already has.
Before the tractor order goes out, get the utility's written view of available capacity at the site and a date for any upgrade. If that date is years away, ask whether software-capped charging could support a first group of tractors on the existing service.
Diesel at $6.53 and a crowded menu
Fuel prices give the operational argument a sharper edge. Heavy Duty Trucking reported on November 8 that the national average on-highway diesel price reached $6.53 per gallon in September. ACT Expo, scheduled for May 17-20 at the Las Vegas Convention Center, is putting a bigger emphasis on costs, efficiency and profitability in its 2027 conference program. Its agenda goes well beyond the event's traditional focus on alternative fuels and vehicle electrification and includes total cost of ownership and return on investment. "This isn't just a sustainability conversation anymore; it's a business imperative," said Erik Neandross, founder of ACT Expo.
That agenda is also the strongest check on reading too much into one uptime figure. It gives equal billing to diesel engine advances, aerodynamics, telematics and right-sizing equipment, and it compares battery-electric with natural gas, hybrid, hydrogen and renewable fuels. Battery tractors are competing for the same capital as cheaper fixes on the diesel side. For a yard whose utility upgrade is five years out, a diesel efficiency project could deliver savings sooner. Buttgenbach concedes the point himself: not every site is a good candidate, and not every operation can electrify at the same pace.
On the other side of the ledger, he argues that EVs offer an alternative pathway that can help reduce dependence on a single fuel source and provide greater flexibility as energy markets fluctuate. He also notes that some regions offer incentive programs that improve project economics. A November 2026 review in Transportation Research Part D, covering more than 100 studies published between 2019 and 2025, points in the same direction from a different fleet type. Looking at battery-electric buses, it identified the central role of optimized charging strategies in total cost of ownership and the need for integrated planning models that jointly consider infrastructure, battery sizing and operations. The review focuses on local public transit companies, and it reports persistent gaps related to uncertainty modeling, scalability for large transport networks and battery degradation. Its findings suggest a lesson for any depot-charged fleet: the charging plan could shape the economics as much as the vehicle does.
Picking the first yard
Buttgenbach's advice is to use fleet and operational data to find the applications where requirements match the technology, rather than forcing equipment into a poor fit. His list of variables works as a screening sheet for ranking sites:
- Duty cycle: how many moves per shift, and how predictable they are
- Charging and utility availability, including the utility's upgrade date
- Operating schedule, and where natural charging windows fall
- Facility layout and the distance between doors, staging and chargers
- Terrain
- Local infrastructure and any regional incentive programs
There is also a path that moves the capital question off a shipper's books. Buttgenbach writes that capital expenditure impacts are minimized when yard operations are outsourced to a trusted partner. For customers that outsource yard operations, he adds, EVs powered by renewable electricity can eliminate indirect Scope 3 emissions while maintaining the throughput and service performance needed to keep products moving. For a shipper whose yard is already outsourced, electrification could become a contract term to raise at renewal rather than an equipment purchase.
The next marker is on the calendar. ACT Expo's early bird registration is available through December 11, 2026, and the 2027 agenda lists charging and energy infrastructure among its topics, covering utility coordination, charging capacity, energy management and challenges in scaling electric fleets. If fleets there report connection times well under the 36 months Harney described, the queue for yard electrification gets shorter. If they don't, the yards that start first will be the ones whose utility said yes first.
Sources
Featured companies
Your experts belong here
Every story in MarketScale Transportation starts with a company putting its fleet managers, logistics engineers, and safety leads on the record. Buyers are already reading this topic. The only question is whose experts they find.
Fleet and logistics buyers compare quietly, and your operators become the evidence that settles it.
About the author
The MarketScale Newsroom reports on the companies, technologies, and trends shaping 16 B2B industries. It turns primary sources and expert commentary into clear, useful coverage for the people doing the work.