India Order Could Free Up 15.7 GW of Renewable Grid Access
India's Central Electricity Regulatory Commission ordered on July 11 that renewable developers surrender transmission rights or provide higher bank guarantees if their projects are not generating power, a change Reuters reported could free up roughly 15.7 gigawatts of grid connectivity. Reuters separately reported that coal still supplies about 70% of India's electricity generation as of an August 17 report.
This story was produced through MarketScale. See how Energy teams put it to work with Customer Stories & Case Studies.
Key takeaways
CERC order requires renewable developers to either surrender transmission rights or post additional bank guarantees for non-generating projects.
Approximately 15.7 GW of grid connectivity held by awarded projects that are not generating power could be freed up; surrendered capacity would first go to existing applicants in the same substation cluster, with any remainder auctioned.
Developers and buyers evaluating projects in constrained substation clusters should verify current CERC connectivity status and guarantee backing, as auction-based allocation may alter cost and timing dynamics.
Get featured
Want to get featured in MarketScale Energy?
Create a free MarketScale workspace and get your company's expertise featured across our Energy coverage. No credit card, no demo required.
India's Central Electricity Regulatory Commission (CERC) issued an order dated July 11 directing renewable energy companies to either give up transmission rights or provide additional bank guarantees if their projects are not producing electricity, according to Reuters, which reported on the order on July 13.
Reuters reported that the change could free up approximately 15.7 gigawatts of grid connectivity currently held by projects that are awarded transmission access but are not generating power. According to Reuters, a large share of renewable capacity awarded between 2019 and 2025 has transmission access but has not yet secured customers.
What the order allows developers to do
Under the CERC order, as described by Reuters, developers have options. They can surrender their transmission connectivity outright, or they can keep it by posting additional bank guarantees while continuing to develop the project on their own. The order also permits transfers of transmission rights within a corporate group, allowing connectivity to move to an affiliated project that is generating power but currently lacks grid access.
Reuters also reported that when connectivity is surrendered, CERC will first offer it to existing applicants within the same substation cluster, with any remaining capacity going to auction.
Coal remains the largest source of generation
Separately, a Reuters Open Interest column published August 17 reported that coal still accounts for roughly 70% of India's electricity generation and remains the backbone of the grid, even as clean energy sources have reached a majority of installed capacity, citing data from Ember and Global Energy Monitor. That column distinguished installed capacity, which reflects what is being built, from generation, which reflects what is actually being run on the grid, and noted that coal plants continue operating around the clock while solar and wind output depends on weather conditions.
A Forbes article published May 10 reported that non-fossil sources reached 50% of India's total installed capacity in June 2025, ahead of the country's Paris Agreement target, and that renewables supplied more than 51% of India's electricity demand in July 2025, according to figures cited in that article. Forbes also cited an estimated $160 billion annual investment gap in modernizing India's power infrastructure.
Why this matters for grid and procurement planning
MarketScale analysis: The CERC order signals that regulators are prioritizing connectivity for projects that are actually generating power over projects still negotiating offtake agreements. Buyers and developers evaluating projects in constrained substation clusters may want to confirm the current status of a project's CERC connectivity and what bank guarantees, if any, back it, since Reuters described higher guarantees as the mechanism for retaining unused connectivity. Because CERC has said leftover capacity will go to auction, interconnection access in constrained areas could carry different cost and timing implications than in the past, though the extent of that effect has not yet been reported.
Sources
- India tells clean energy firms to lose grid connection or generate power (July 13, 2026) ↗ · Reuters
- India's power system just passed a historic tipping point (Aug. 17, 2026) ↗ · Reuters
- India's Power Boom Has an Evening Problem (Aug. 13, 2026) ↗ · Bloomberg
- India's Grids Must Now Be Smart Enough For Clean Power (May 10, 2026) ↗ · Forbes
Your experts belong here
Every story in MarketScale Energy starts with a company putting its field engineers, operations leads, and project developers on the record. Buyers are already reading this topic. The only question is whose experts they find.
Developers and operators shortlist on credibility, and your engineers give your sales team something real to send.
About the author
The MarketScale Newsroom reports on the companies, technologies, and trends shaping 16 B2B industries. It turns primary sources and expert commentary into clear, useful coverage for the people doing the work.