Grid approval will decide the size of a planned 150 MW Haifa data center
Enlight Renewable Energy and Shemen Yielding Real Estate plan an up-to-150 MW Haifa data center, backed by NIS 334 million in bank guarantees. Power decides the rest. Site size, rent and timing all wait on Israel's Electricity Authority, which has roughly 1,000 MW of data-center capacity left to allocate.
This story was produced through MarketScale. See how Energy teams put it to work with Customer Stories & Case Studies.
Key takeaways
The Haifa site will be either 41 to 57 dunams or the full 82, based on the approved grid connection capacity and planning and technical considerations, so the grid decision will help set the footprint.
NIS 334 million in guarantees for a 150 MW application works out to a little over NIS 2.2 million per megawatt, a reference point for what holding a place in Israel's data-center grid queue costs.
Rent starts around NIS 27,000 per dunam during development and rises gradually to NIS 433,000 per dunam once the data center is operating, keeping land costs lower before the facility opens.
Free workspace
Turn your Energy expertise into content.
Record interviews, organize footage, and write with AI on a free trial of the MarketScale platform for qualifying companies. No demo required, no credit card.
Nobody has ordered a single rack for Haifa yet, but Enlight Renewable Energy and Shemen Yielding Real Estate have already agreed to put up bank guarantees currently estimated at NIS 334 million. The two companies signed a strategic cooperation agreement on Nov. 16 to develop, finance, build and run a data center with planned capacity of up to 150 MW on land Shemen owns in the Hof Shemen area of Haifa, according to their joint announcement on GlobeNewswire. Each partner will own 50% of a dedicated project company. Enlight leads development, construction and operations, and the two sides split the cost of moving the project forward.
The guarantees explain what this deal really is. Israel's Electricity Authority has published a proposed decision on how data centers connect to the grid. The partners have filed a 150 MW connection application and received confirmation that the paperwork is complete. The project can move forward only once the regulatory framework is finalized, the grid connection is approved and the other required approvals come through, including a binding final decision from the authority.
For anyone planning compute capacity in Israel, the sequence here could be instructive. The partners filed for power before the project's land allocation was set, and that allocation will follow the approved connection capacity along with planning and technical considerations.
Israel's remaining 1,000 MW
Ctech's Daniel Shmil described the deal as the newest entry in a crowded race for Israeli data-center power. The Electricity Authority's framework shows why the race is crowded: most of the power set aside for data centers has already been claimed.
How Israel's data-center power is divided
Ctech by Calcalist; Enlight Renewable Energy and Shemen Yielding Real Estate
Against the open pool, this is a big bid. By our arithmetic on Ctech's figures, 150 MW equals about 15% of the capacity still available. Ctech also reports that applicants must post financial guarantees to secure grid connections under the authority's framework. Divide the NIS 334 million by the 150 MW requested and the commitment comes to a little over NIS 2.2 million per megawatt. That is our calculation, not a published rate.
The guarantee requirement suggests the regulator could be using money on the table to separate committed projects from speculative filings. For developers and landowners weighing an Israeli application, the estimated NIS 334 million gives a sense of how much money a grid bid can tie up before any tenant signs. Enlight and Shemen will provide the guarantees in equal shares.
A lease that waits for the megawatts
The agreement covers about 82 dunams, which the companies put at roughly 20 acres. It doesn't commit all of it. The final allocation depends on approved grid capacity and on planning and technical considerations, and it will be one of two options: 41 to 57 dunams (about 10 to 14 acres) or the whole site. Ctech describes the range more loosely, as between 41 and 82 dunams.
Enlight and Shemen applied for 150 MW before settling the footprint: the site will be 41 to 57 dunams or the full 82, depending on what the grid regulator approves.
The rent follows the same logic. The announcement sets annual rent at NIS 433,000 per dunam, or a pro rata amount, linked to the Israeli Consumer Price Index from signing, over a term of about 25 years. Total lease payments are expected to exceed NIS 500 million. Ctech adds the detail that matters for cash flow: rent starts at NIS 27,000 per dunam during development and rises gradually to the full rate once the data center is operating.
Apply the operating rate to the possible footprints and annual rent comes to about NIS 17.8 million for 41 dunams, NIS 24.7 million for 57 and NIS 35.5 million for the full site, before indexation. Those are our calculations on the published per-dunam rate. Rent starts at NIS 27,000 per dunam during the development phase and rises gradually, which suggests holding the land costs relatively little before the facility opens. The full operating rate applies once the facility is running.
Enlight and Shemen applied for 150 MW before settling the footprint: the site will be 41 to 57 dunams or the full 82, depending on what the grid regulator approves.
The land option points the same way. Enlight, or an affiliate it controls, can buy a 50% interest in whatever land is allocated to the project at no less than NIS 6.3 million per dunam, according to the announcement. Ctech puts the floor at NIS 6.32 million, says the price can rise under a pre-agreed mechanism, and reports the option can be exercised 30 months after signing. Counting 30 months from Nov. 16, 2026 puts that window around May 2029. At the floor price, half of a 41-dunam allocation would cost roughly NIS 129 million, again our arithmetic. The option gives the operator a route from tenant to co-owner of the ground under its own facility once the project's size is known.
A solar developer with a waterfront parcel
Enlight, founded in 2008, develops and operates utility-scale solar, wind and energy storage in the United States, Israel and Europe. It reported a total portfolio of 46.2 FGW as of Sept. 30, 2026. CEO Adi Leviatan tied the move to the power demand created by AI and computing investment. He said Enlight's data-center strategy targets locations that combine suitable land, power infrastructure and proven construction experience.
This isn't Enlight's first Israeli data-center project. According to Ctech, Enlight won an Israel Land Authority tender in March 2025 to build a data center next to a solar facility at Ashalim, in the Negev. Shemen brings the other half of the deal. It succeeded Shemen Industries, a former oil producer, and now holds 12 logistics, industrial and storage properties, including a parcel in the Haifa Port hinterland. CEO Dan Sheffi described the partnership as a way to realize the full potential of the Hof Shemen site.
The split of roles is clear. The landowner brings the site, and the energy developer brings grid filings, financing and large-project construction. For owners of industrial land, the Haifa terms suggest that approved grid capacity could shape how much of a parcel a project ends up using. The deal is still early, though. Mugglehead noted that the announcement names no data-center customer, construction budget, electricity-supply price or opening date. Until those details appear, operators tracking Israeli capacity may want to treat Hof Shemen as a pipeline project.
The ruling that sets the schedule
The next gate is the Electricity Authority's binding final decision on data-center grid connections. The 150 MW application can move forward only after that decision and the other required approvals. The approved connection capacity, along with planning and technical considerations, will then decide which version of the Hof Shemen campus gets built. The lease, the rent ramp and the land option are all written to handle either outcome.
When shortlisting Israeli data-center capacity, ask each provider whether its grid connection is approved or still an application under the proposed framework, and how many megawatts the approval covers. For the Haifa project, the approved connection capacity will help set how much of the site is used, and the project cannot advance without grid approval.
When the final decision lands, two things are worth checking. First, whether the guarantee requirement survives in its proposed form. Second, how the roughly 1,000 MW still open gets divided among the developers competing for it. The amount awarded at Hof Shemen will show which of the two footprints Enlight and Shemen actually build.
Sources
- Enlight Renewable Energy and Shemen Yielding Real Estate Sign Agreement to Advance Development of a Data Center With Planned Power Capacity of Up to 150 MW in Israel ↗
- Enlight Renewable Energy and Shemen Yielding Real Estate ↗ · GlobeNewswire
- Enlight and Shemen plan 150MW data center at Haifa port site | Ctech ↗
- Enlight Renewable Energy signs deal for up to 150 MW ↗
Featured companies
Your experts belong here
Every story in MarketScale Energy starts with a company putting its field engineers, operations leads, and project developers on the record. Buyers are already reading this topic. The only question is whose experts they find.
Developers and operators shortlist on credibility, and your engineers give your sales team something real to send.
About the author
The MarketScale Newsroom reports on the companies, technologies, and trends shaping 16 B2B industries. It turns primary sources and expert commentary into clear, useful coverage for the people doing the work.