# Jacobs and TYLin get up to $150M to help Washington's airports manage overlapping builds

By MarketScale Newsroom · Published 2026-11-19 · Engineering & Construction on MarketScale
Canonical: https://www.marketscale.com/industries/engineering-and-construction/jacobs-and-tylin-get-up-to-150m-to-help-washingtons-airports-manage-overlapping-builds

> MWAA's task-order contracts with Jacobs and TYLin, capped at $150M, cover program management as Dulles' Package T and Reagan National's Terminal 1 advance.

## Key points

- Washington's airport authority secured up to $150 million of outside program management before Dulles' Package T tunnel work has been solicited, because it expects simultaneous projects to exceed its own staff and existing contractors.
- Even at its full 10-year, $300 million ceiling, the oversight pool serves a Dulles redevelopment valued at more than $20 billion, and it also covers Reagan National.
- The first task orders will show whether Jacobs mainly leads Package T or provides staff across both airports. Package T responses are due Nov. 23 and Reagan National construction manager at-risk proposals are due Dec. 7.

The authority that runs Washington Dulles International Airport says extended train tunnels and a new underground network will eliminate the need for mobile lounges and plane mates to carry passengers. The network would link concourses that sit as far as about 3,500 feet apart. On Nov. 17, Jacobs said it will help manage that work.

The contract runs five years and covers both Dulles and Ronald Reagan Washington National. Dallas-based Jacobs Project Management Co. and San Francisco-based TYLin International each received their own task-order contract from the Metropolitan Washington Airports Authority (MWAA), Engineering News-Record's Bryan Gottlieb reported, citing procurement records. Under a July 15 board resolution, combined spending is capped at $150 million over five years. If MWAA exercises five one-year options, the ceiling could reach $300 million across a decade.

The structure tells the story. MWAA locked in up to $150 million of outside program managers while Package T was still at the request-for-information stage, because the authority expects its simultaneous projects to outrun its own staff and existing contractors. That matters to contractors chasing the Dulles tunnels or the Reagan National terminal. For years, the people administering their contracts could come from these two firms.

## How the $150 million ceiling gets spent

Neither firm is guaranteed $150 million, or any fixed share of it. MWAA pays only as it issues task orders, and specific assignments haven't been disclosed. The July board action, Resolution 26-9, sets the figure as an estimated not-to-exceed spend, and its title describes the award as program management support and staff augmentation services. That second phrase suggests much of the money buys people who work inside MWAA's own organization rather than standalone deliverables.

The scope is broad. It covers construction management, contract administration, project controls, finance, environmental reviews, engineering oversight and planning. Jacobs' own announcement also lists staff augmentation for administrative and technical engineering tasks.

The program those people will serve has grown fast. ENR puts the Dulles redevelopment at more than $20 billion, up from about $7 billion before the U.S. Department of Transportation selected a proposal in July. Construction Dive's Sebastian Obando put the overhaul President Donald Trump unveiled that month at $22.5 billion. That plan followed a DOT review of more than 30 proposals submitted the previous December. The two outlets' totals differ, but both describe a program roughly triple its earlier size.

Block Field

Spread evenly, the initial ceiling comes to about $30 million a year across both firms. That figure is simple arithmetic on MWAA's cap, not a spending rate the authority has published. Actual spending could cluster around whichever packages are in design or under construction at a given time.

Even at the full 10-year ceiling, the pool tops out at $300 million. The Dulles program alone is valued at more than $20 billion, and the contracts also cover Reagan National. Airport capital directors elsewhere shouldn't read the pool as a full program-management budget. MWAA is adding these contracts to its own employees and existing contractors, so the figure suggests only what it is spending on extra staff.

## What the Dulles money builds

Jacobs' release sketches the scope at Dulles: new international and domestic concourses, an expanded central processing area, updated check-in, security and baggage systems, and new concourse connectors meant to give travelers more predictable routes. Inside the concourses, it promises expanded gate areas, with new retail and dining placed in high-traffic zones. ENR reported in July that Package A would add or renovate gates, security areas, baggage systems and a post-security connector to Concourse A.

All of it wraps around a building that stays. ENR notes that the Eero Saarinen-designed main terminal will be preserved, and Jacobs Chair and CEO Bob Pragada described the work as "blending thoughtful modernization with the timeless architecture that makes these spaces unique." For oversight staff, that means new capacity added around and beneath a landmark that keeps operating while the work goes on.

## Package T and its underground neighbors

In Jacobs' announcement, MWAA President and CEO Jack Potter singled out Package T, the extension of Dulles' underground train and related work. He called it a key part of the authority's Dulles Global Gateway initiative and cited Jacobs' experience on MWAA's Metrorail Silver Line construction, saying the firm "will be instrumental in moving this important project forward." MWAA issued a request for information on Oct. 21. It asks prospective progressive design-build teams for input on scope, procurement strategy and construction risk.

ENR's account of the request breaks the package into an extension of the existing system and a new network:

- Extending the automated people mover to Concourse C West and Concourse D West with new tunnels and systems, work that procurement documents call Tier 2 and Tier 3
- Tunnels linking Concourses A, C and D so passengers can move between them without going back through the main terminal
- Links that take international arrivals out of Concourse C to a planned federal inspection facility
- An underground baggage system connecting the main terminal with the concourses

Timing is the hardest part. According to MWAA, three other major construction packages will be underway while Package T is being designed and built. Tunnels, stations and concourse structures have to be coordinated so finished work doesn't have to be redone. Package A, the terminal procurement, leaves out the major AeroTrain extensions, but its infrastructure still has to be built to accept those future connections. Handoffs like these fill the days of project controls and contract administration staff.

Concourse A shows where the seams could fall. Package A carries the post-security connector to it, while Package T's tunnels would tie it to Concourses C and D, so two separately procured packages would converge on the same concourse.

The request reflects the same concern. It asks for recommendations on utility surveys, construction logistics, contract structures and risk allocation. It also asks firms to describe their experience with underground stations, tunnel ventilation, life-safety systems, baggage conveyance and construction inside an operating airport.

Steve Pelham, Jacobs' aviation market director for the Americas, said in the release that modernizing airports while they stay fully open requires careful sequencing and close work with the operator, the airlines and the delivery teams. He named United Airlines among the stakeholders. Jacobs also says the program leaves room to explore high-speed moving walkways and small autonomous shuttles.

### Reading Jacobs' role

Potter's comments could point to a different role. He tied Jacobs directly to Package T, which suggests at least part of the firm's work could be leading a single package rather than lending staff across both airports. Construction Dive read the statement the same way, reporting that Jacobs will assist with Package T at Dulles. The resolution allows for either, and the early task orders will show which one MWAA chose.

Jacobs also arrives with history at the authority. Commercial Construction & Renovation reported that MWAA earlier selected Jacobs for facilities condition assessment and enterprise asset management services at both airports. That work covered how buildings and infrastructure are managed, capital investment needs and which maintenance and repair projects come first. It used the same architecture as the new award: a five-year term built from a base year plus one-year options.

Beyond Washington, Jacobs says ENR has ranked it No. 1 in aviation for the second consecutive year and that it works at more than 150 airports. Its U.S. list includes Hartsfield-Jackson Atlanta, Los Angeles International, Denver International and the terminal expansion at Baltimore/Washington International Thurgood Marshall.

## Reagan National on a parallel track

At Reagan National, MWAA plans to replace the older Terminal 1 gate for gate and redevelop the airport's South Area. Airport manager Terry Liercke told ENR in a July 2025 interview that a design firm had been chosen for the replacement terminal, which will connect to the historic 1941 terminal building. He said the issues under review include security checkpoints, ticket counters, baggage claim and roadway access.

An Oct. 9 solicitation seeks a construction manager at-risk for preconstruction planning and construction support on Terminal 1 and the South Area. Proposals are due Dec. 7. Because the scope starts in preconstruction, the winning team would be involved early, working beside whatever oversight staff MWAA assigns through the Jacobs and TYLin contracts. Builders pursuing both airports will be dealing with the same owner, the same pool of outside oversight staff and procurements that overlap.

Block Field

## Two deadlines before year end

Package T responses are due Nov. 23, four days from now. MWAA will use them to shape its procurement strategy, and the request isn't a construction solicitation or a contract award. Reagan National's CMAR proposals follow on Dec. 7.

After that, watch the first task orders issued under the July resolution. Whichever firm gets the work where Package T meets Package A will show how MWAA plans to manage four construction packages in the same ground under Dulles.

## Sources

- [Jacobs, TYLin Win $150M Washington, DC Airports PM Contracts](https://www.enr.com/articles/64334-jacobs-ty-lin-win-150m-washington-airports-program-management-contracts) (Engineering News-Record)
- [Jacobs selected for multi-year Washington DC area airport modernization program | Jacobs](https://www.jacobs.com/newsroom/press-release/jacobs-selected-multi-year-washington-dc-area-airport-modernization-program)
- [Jacobs, TYLin win $150M contract on Dulles, Reagan National airport ...](https://finance.yahoo.com/real-estate/articles/jacobs-tylin-win-150m-contract-214000200.html)

Tags: Jacobs, TYLin, Metropolitan Washington Airports Authority, Dulles Package T, Reagan National Terminal 1, airport program management

---
Source: MarketScale, https://www.marketscale.com/industries/engineering-and-construction/jacobs-and-tylin-get-up-to-150m-to-help-washingtons-airports-manage-overlapping-builds. Published for AI indexing and citation; cite the canonical URL. Site guide for agents: https://www.marketscale.com/llms.txt