# Data-center developers face a new approval map after the midterms, starting in Texas

By MarketScale Newsroom · Published 2026-11-05 · Energy on MarketScale
Canonical: https://www.marketscale.com/industries/energy/data-center-developers-new-approval-map-midterms-texas

> Local opposition and new state leadership are making community approval and power access the deciding factors for data-center projects, and developers say they plan to keep building.

## Key points

- Texas governor-elect Gina Hinojosa pledged to ban data-center approvals until the legislature passes new laws, Reuters reported.
- The Data Center Coalition said members would keep building in Texas while working with state and local governments.
- Under an ERCOT process being finalized, projects must certify local approvals to qualify for accelerated interconnection, Argus reported.

Local opposition to new data centers has become one of the main questions hanging over AI infrastructure, and Tuesday's midterm elections put it at the center of state policy. In Texas, governor-elect Gina Hinojosa campaigned on banning data-center approvals until the legislature passes laws giving Texans "a seat at the table to decide if and how data centers come into our community," Reuters reported.

For developers, utilities, builders and equipment suppliers, the shift is less about whether data centers get built and more about how: community approval, power availability and local rules are becoming the deciding factors for where projects go next.

## How Texas got here

Texas became one of the world's leading regions for data-center development on plentiful energy, relatively cheap land and pro-business policy, and Meta, Google and Microsoft have all announced major projects there, according to Reuters. The state has about 87 operating data centers and roughly 156 planned projects, according to industry figures presented by law firm Baker Botts and reported by Argus.

On August 3, Gov. Greg Abbott halted the connection of new data centers to the state grid and ordered an audit focused on power demand, environmental impacts and tax breaks, Reuters reported. By then, ERCOT was tracking more than 400 gigawatts of data-center projects seeking to connect.

At the local level, counties and cities have proposed or enacted moratoriums, denied zoning requests and added restrictions, citing water use, grid strain, noise and the industrialization of rural areas, Argus reported. Hill County approved a moratorium that developers are now challenging in court, San Marcos denied a rezoning request and San Angelo adopted new setback and noise rules. Round Rock, by contrast, approved a project despite opposition.

## Developers say they will keep building

The Data Center Coalition, which represents Big Tech and other developers, said its members would continue to pursue their build-out in Texas while working with state and local governments. "Data centers can continue to play a crucial role in advancing those priorities by bringing investment to local communities," said Jess Heck, the coalition's Texas director of government affairs, according to Reuters.

Austin McCarty, a government affairs adviser with K&L Gates, told Reuters that some projects may be delayed or leave the state, while others are expected to speed up completion and power-up before new restrictions take hold. "It's a brand-new day in Texas for a ton of what was probably considered settled policy," he said.

Brittany Kaiser, CEO of developer Alpha Compute, said developers now need to engage directly with legislators, regulators and communities and go beyond regulatory compliance to be good neighbors, Reuters reported. She said developers without signed contracts and financing are more likely to look at other states or at Canada, Mexico and Europe.

## What B2B teams in the data-center supply chain can watch

Local approvals now carry more weight in grid access as well. Under a process being finalized by ERCOT, projects must certify they have secured all required local approvals, or that none are needed, to qualify for accelerated interconnection, Argus reported. Baker Botts partner Juliana Sersen noted that the rule does not distinguish between lawful and unlawful local actions.

For energy, construction, industrial automation and computing suppliers, that makes early community engagement, water and power planning, and clear answers on local costs part of the sales conversation. Projects that already have approvals, contracts and financing in place are the ones developers say are most likely to move ahead, while new state rules take shape in Texas and other growing hubs.

## Sources

- [Texas data centers face uncertain future after Hinojosa wins governor's race](https://finance.yahoo.com/technology/articles/texas-data-centers-face-uncertain-172340564.html) (Reuters)
- [Local opposition builds to Texas data centers](https://www.argusmedia.com/en/news-and-insights/latest-market-news/2832636-local-opposition-builds-to-texas-data-centers) (Argus)
- [$64 billion of data center projects have been blocked or delayed amid local opposition](https://www.datacenterwatch.org/report) (Data Center Watch)

Tags: Data Centers, Texas, ERCOT, Site Selection, Energy, AI Infrastructure

---