> MoMA won two World Championship for Energy Savings awards. Just over half of its 34% energy cut came from equipment replacements it needed anyway.

## Key points

- At MoMA, 51% of the energy reduction came from capital projects driven by end-of-life equipment, work the museum would have needed with or without a carbon law.
- A 33% carbon cut clears Local Law 97's 14% requirement for 2024 but still sits short of the 50% required by 2030. A heat pump chiller and the next round of plant replacements are expected to close that gap.
- For 24/7 buildings with major equipment nearing end of life before 2030, MoMA’s case suggests combining the replacement plan and the carbon compliance plan into one document can help.

More than 300,000 building automation control points. 237 air-moving units. Systems that must operate 24/7/365. That's the building New York's Museum of Modern Art entered in an international energy competition, and it came away with two of the prizes.

Grumman/Butkus Associates (GBA), the engineering firm that has advised the museum since it commissioned the LEED Platinum Geffen Wing, reported that MoMA won the Deep Emissions Reduction Award and the Most Improved Energy Use Award in the World Championship for Energy Savings. The competition is a Global Alliance for Buildings and Construction initiative. Its American division, the USA National Energy League, is run by the US Green Building Council, and this year it drew buildings from 16 countries. MoMA was recognized at the Global Impact Summit during the recent Greenbuild International Conference & Expo, and again at a ceremony in Turkey.

The headline results are strong: energy use down 34% and carbon down 33% against a 2019 baseline. The more useful number comes later in GBA's account. Capital projects made up 51% of the energy reduction, and the museum would have needed those projects no matter what, because the equipment was wearing out.

That changes the budget conversation for anyone running an older 24/7 building under a carbon cap. If an aging chiller plant has to be replaced anyway, the compliance plan and the replacement plan can be written as one document, and MoMA is now a public, award-verified example of what that produces.

Block Field

## Eighty-seven years of additions, one plant

MoMA's campus began with the Goodwin-Stone building in 1939 and has grown into several connected facilities totaling 743,825 square feet. Everything runs 24/7/365 on a central chiller plant and district steam. GBA's project page lists the inventory its retro-commissioning team tested: four chillers and their pumps, four cooling towers, four pre-treatment air handlers, more than 100 primary air-handling units, and a Honeywell automation system that combined digital and pneumatic controls.

The relationship predates the carbon work. GBA first retro-commissioned MoMA's chiller plant, which led to a plant expansion, and then commissioned a major facility expansion completed in 2019 before being retained for ongoing sustainability and infrastructure planning. That puts the baseline year at the moment the newest space came online. The 34% cut, in other words, was taken from a campus that already included a LEED Platinum wing, which suggests the savings came from running the whole plant better rather than from retiring one obviously outdated building.

Block Field

Heating comes from 150-psig Con Edison steam, which enters through three main pressure-reducing valves and feeds three steam-to-hot-water converter stations (six converters in total) plus the humidification equipment. That matters for the results. In a building that heats and humidifies with purchased steam, every steam fix shows up directly on the utility bill and in the carbon calculation.

Scale like this is also why the work started with measurement rather than shopping. More than 9,000 points are now trended continuously through GBA's monitoring-based commissioning platform, Trend Sumo. That gives the team a running record of which systems are drifting before anyone signs a capital request.

GBA's project page calls a specific set of measures foundational: automation upgrades to enable better monitoring, end-use metering and dashboards, and fault detection. Putting them first fits an award built on verified data. A building has to measure a system before it can prove that a fix to that system is holding.

## Three tracks with different paybacks

Two pressures started the museum's new capital plan. One was New York City's Local Law 97, which phases in carbon intensity limits for large buildings and carries heavy fines for missing them. The other was equipment at or near the end of its life, with the reliability risks that come with it. GBA's energy study, retro-commissioning project and facility assessment turned both into one strategy: targeted maintenance, repairs and adjustments to the automation system, and phased upgrades to the HVAC and lighting.

Local Law 97 is only one of several city sustainability laws MoMA has to satisfy. GBA's scope included benchmarking, calculating the Local Law metrics and helping with the museum's LL84 and LL97 submissions, so the reporting and the engineering came from the same team.

The program ran on three tracks:

- Capital projects: end-of-life replacements and resilience priorities.
- Targeted energy projects: discrete measures with simple paybacks under five years.
- Operational optimization: low-cost and no-cost changes to sequences and procedures.

The tracks don't carry equal weight. At MoMA, 51% of the energy reduction came from projects the museum would have needed regardless of Local Law 97 or its own sustainability goals. That suggests the extra spending the carbon law forced is much smaller than the total project budget would imply. It's a useful distinction for a CFO comparing compliance costs with fine exposure.

Outside money helped too. Utility incentives and foundation grants have covered about 20% of costs so far. GBA wrote the energy master plan in the format approved by NYSERDA's FlexTech program and supported the incentive applications, which shows that the paperwork was planned from the start rather than added at the end.

The consulting also ran past the report itself. Implementation support included narratives, sketches and help soliciting proposals from contractors, along with recommendations for upgrades that would let the museum take part in a real-time energy management program. For a facilities team with a full operating load, that handoff from study to bid documents is often where a plan either moves or stalls.

The most delicate decisions were about temperature and humidity. The team reviewed the museum's existing setpoints and changed them after long conversations with staff, guided by the Bizot Green Protocol, an international guideline for running museums efficiently without endangering collections or loans. GBA's list of retro-commissioning measures fills in the rest: air-handler optimization, steam distribution tuning, condensate heat recovery, demand-controlled ventilation on lab and kitchen exhaust, and a new chilled glycol system for cool and cold archival storage. The firm also ran a laboratory ventilation risk assessment with specialist firm 3Flow.

Domestic water system upgrades and new lighting fixtures and controls completed the initial list. The measures were split into two phases, with priorities worked out together with the museum as owner.

## Steam fell faster than electricity

Block Field

The order of the work is visible in GBA's milestone chart for 2021 to 2026. Retro-commissioning and setpoint changes came first. Next came a new steam pressure-reducing valve and lighting upgrades, followed by an automation controls upgrade that shows up as two separate steps, one at 50% complete and one at 100%. Cheap fixes went in before expensive hardware, so each later project started from a lower, better-understood baseline.

District steam fell 36% and electricity 31%, which fits a program that put early attention on steam valves and distribution. GBA reports that the 33% carbon cut far exceeds Local Law 97's 2024 requirement of 14% for the building and is on track for the 50% required by 2030. By simple subtraction, 17 percentage points still need to come out over the next four years.

Per square foot, energy use fell 36%, slightly more than the 34% drop in total annual MMBtu. The intensity figure is the one owners should watch, since Local Law 97 sets its limits as carbon intensity rather than as a fixed total.

GBA's waterfall chart for 2030 shows where it expects those points to come from, with groups of measures stacked toward the target. A heat pump chiller, still to be installed, plays a major role. The second phase on the project page is bigger: new chillers and cooling towers and more than 100 air-handling units, in a multi-year program that's still underway. The firm credits ongoing utility monitoring, metering, and fault detection and diagnostics with keeping the savings from slipping as the building changes.

## Where the museum playbook travels

GBA argues the lessons apply to other energy-intensive buildings: hospitals, labs, academic buildings, data centers, multifamily housing and hotels. The common thread is a building that can't shut down and has systems approaching replacement. For owners whose major equipment reaches end of life before 2030, the 51% figure is the one to bring to the capital planning meeting.

The argument has limits. That 51% share depends on timing. A building that replaced its chiller plant five years ago can't count that work as compliance progress, and it will lean harder on the under-five-year projects and the operational track. The setpoint changes also relied on a museum-specific guideline that gave curators and engineers a shared standard to point to. A hospital or lab would need to base any comparable change on the guidance that governs its own spaces.

Block Field

Two more questions follow from MoMA's sequence. Have the setpoints been examined, with the people who own the spaces, before anyone sizes new equipment? And is enough of the building trended continuously to prove savings are holding? The museum had more than 9,000 points under watch when it went in for verification.

The next thing to watch is the heat pump chiller. GBA's 2030 plan depends on it, and once it's running, the museum's carbon curve will show whether the remaining 17 points come as smoothly as the first 33.

## Sources

- [MoMA Honored For World-Class Energy Savings](https://grummanbutkus.com/blog/moma-honored-energy-savings/)
- [The Museum of Modern Art | GBA](https://grummanbutkus.com/projects/moma-sustainability-master-plan/)

Tags: Museum of Modern Art, Grumman/Butkus Associates, Local Law 97, retro-commissioning, World Championship for Energy Savings, Trend Sumo

---
Source: MarketScale, https://www.marketscale.com/industries/building-management/just-over-half-of-momas-award-winning-energy-savings-came-from-replacements-it-needed-anyway. Published for AI indexing and citation; cite the canonical URL. Site guide for agents: https://www.marketscale.com/llms.txt